Dear all,
Below are the minutes of the meeting with Surrey
County Council on 28th January 2005. Obviously your voice is being heard as
this was an unprecidented event. SCC felt moved to meet us due to the
weight of your protest.
Meeting SCC, RPS and CAMEL
28th January 2005
Meeting Report
Present:
Simon Elson Minerals and Waste Team SCC
Hilary Herbert Minerals and Waste Team SCC
David Lamb Minerals and Waste Team SCC
David Batey CAMEL
David Evans CAMEL
Bert Smith CAMEL
Susan Snook CAMEL
Nick Snook CAMEL
Paul Tanner CAMEL
Nick Hayward RPS
Frances Russell RPS
Overview
Group met at Heath Cottage and walked PMZ60, proceeded to Reigate Heath
Windmill to see the greater view of the Zone, set within the context of the
Surrey Hills, and returned to Heath Cottage.
Group then comprehensively toured PMZ55 by car, taking in all views of the
zone, from Brockham and Betchworth. Parked at bottom of the Common Field, walked
through churchyard and up The Street and back down the footpath within the
Zone.
Repaired to The Old Vicarage, Old Reigate Road for meeting.
Designation of PMZs
DL: The Landscape appraisal of mineral sites advised against those within
AONBs owing to the nature of that designation. The landscape study had been
completed by CBA and it was not planned to go into any greater detail. Those
sites studied by CBA, in addition to the 26 ‘included’ at present, are to be
seen as reserve sites. This contradicted what was stated later in the meeting
when DL commented that there were no reserve sites at present. The
additional handful of sites studied by CBA included 57,58 and 59. DL said
additional sites had been selected on grounds of environmental sensitivity. HH
stated (see below for detail) that since Ashcombe, the SCC aggregate requirement
had risen with the effect that 6/26 sites may not now be knocked out at the next
stage (as had been suggested at Ashcombe).
HH: context of all guidelines within SCC Plan 2004 are relevant to the
current sites, they should not be viewed individually. DL: there are many
policies and these need to be weighed up together. HH added that the Zones
needed to be in compliance with these policies.
The Surrey Structure Plan existed for three further years when regional
(South East England Regional Assembly, SEERA) would supercede. However, HH noted
that the SCC policies were in greater detail to the regional ones. HH commented
further that while SCC had lost the Structure Plan role, it had maintained
minerals and waste.
SCC made presentations to SEERA in October on mineral and waste policies and
this had been published at the beginning of January. This report had gone to the
Government who will consult in March with recommendations. It was noted that the
Panel report put the needs of the construction industry above environmental
concerns.
RPS had received pack from SCC re compliance for sites.
Summary of Objections
So far SCC had received 1,000 letters of objection. There had, however, been
some 50 duplicates (ie 950 ex duplicates). Of these 1,000 letters, 80 had been
from statutory bodies or interest groups, the rest from individuals.
The nature of objections: for PMZ60 traffic, effect on Heath, hydrology,
landscape and recreation. For PMZ55 the impact on village from loss of common
field and traffic. DL had noted importance of footpath during the morning’s
tour, but stated that this footpath would not be lost if quarry went ahead.
The objections are available to public view (DL), but they were being
analysed presently. HH stated that this analysis would take some time; the delay
in the objection deadline had pushed this analysis back.
NS asked for further, more detailed, information on the areas within the PMZs
which are of interest, quoting DL’s standard letter of response to objections in
which this information is offered.
At Ashcombe we had been invited to correct the Framework document. PT asked
for comment on which corrections had been accepted. DL noted ‘quite a lot’ of
factual corrections, as well as subjective assertions, in the document as a
whole, which will be taken into account. PT commented that these errors
undermined the confidence of local villagers and that if this Framework PMZ
assessment were to be the foundation for decisions, these errors would
necessarily undermine confidence. HH responded that we were at a verification
stage presently.
Nutfield is the other area in Surrey of greatest objection. These objections
were largely traffic and hydrology. Alton Road in Spelthorn, NW Surrey, is also
objecting strongly. Despite the fact that Spelthorne relates to gravel
extraction, they are effectively in competition with us as SCC’s targets were
for overall aggregate; sand and gravel are not separately apportioned.
Process and Timescale
HH commented that as SCC had received objection to this Framework it was
bound to go to enquiry. DL added that the Government assume that more
consultation initially will give rise to fewer objections.
HH: The minerals and waste development scheme had just been submitted to
Government. The date for an inspector for enquiry may be some way off, however,
the Government had given housing and waste priority. This, coupled with the new
system has put pressure on the inspectorate. SCC had been charged with the task
of being ready by 2007, therefore all enquiries should be completed by 2006.
However, if housing and waste was to be prioritised over minerals (against SCC
wishes as minerals work is currently underway) then the enquiry may be delayed.
- The current, first stage of is informal information gathering and
correction of data.
- Formal consultation in October (6 wks max – govt stipulation) of draft
plan identifying preferred sites (twin-tracking it with waste plan)
- Further formal consultation stage of 6 weeks when revised document is
submitted (2006) to Government office. Further presentations at that stage
would go to public enquiry.
- Public enquiry
Government’s target to SCC is three years to form process, but there is no
limit to the public enquiry timing if there should be a clash of interests with
housing and waste (Sept 2007 current deadline).
HH: Corrections to original PMZ report would be published on SCC
website in October. From analysis of letters categories of objection to be
identified which SCC will respond to. HH would endeavour to be as open as
possible with information in this regard.
NH asked whether, at the end of February, SCC would take the corrected report
to an appropriate committee prior to selecting PMZ options. The response was
negative. The key decision maker was the Environment Portfolio holder (David
Davis, note election in May). The Task Group: Environment & Economy Select
Committee, Executive Committee will meet at the end of September for formal
decision on PMZs. The draft preferred options plan will go to public
consultation in October. The minerals and task was group not open to the public
but we could be given member names so that CAMEL can lobby. There is an
allowance within Freedom of Information for members to have private time to
review documents prior to public views.
Confidence in Process
CAMEL had commented on lack of confidence locally in the selection process.
SE: gave the example that the Framework document was not in fact incorrect in
stating that PMZ55 was 300m from the village, as the professional norm was to
take the mid-point from the site. PT corrected this assertion; even taking the
mid-point protocol, the statement was incorrect. NS added that the cross
reference within the PMZ60 section was unnecessary, relating to a few short
lines of text which makes the document difficult to access.
Betchworth Quarry had conditions imposed within the planning approval, but
these had not been effectively policed. HH stated that there were enforcement
officers with this task. DE cited the December 2004 closure condition which had
not been enforced at Betchworth. The Reigate Road Quarry (Franks) was also mined
at variance to planning conditions, notably the face was being undercut which
was potentially unsafe, but nothing had been done to correct the practice. These
omissions undermined public confidence. Why one rule for contractor and another
for public? HH took note and will look into this and ask enforcement officer to
investigate these examples.
SE: Agreed that these assertions were correct. There had been a meeting at
Betchworth Quarry at the end of 2004 to establish final cessation of works.
These sites were inspected regularly and the Betchworth meeting had addressed
that particular issue. The Betchworth situation was difficult, however. DE asked
whether there had been a private deal, HH responded that there hadn’t been. DE
retorted that if there had been no planning application for variance to
conditions stipulated previously, yet these activities were continuing with
SCC’s agreement but without Planning Approval with its inherent public
accountability, this constituted a private deal which leads to lack of public
confidence in the process.
DE: Where documents were incorrect, publishers should take responsibility and
correct them so that readers new to the issue would have a correct
understanding. DE gave the example that a judge at a Public Enquiry would absorb
the facts contained within the first document he read. If this happened to be
incorrect, it would be difficult to shift perceptions once the correct
information had been furnished.
DE requested that the initial document be withdrawn and a corrected document
put in place. HH simply stated that our comments would go forward to draft plan
stage.
DE appreciated that while sand is clearly needed, it should be extracted from
non-sensitive sites.
In answer to this, DL outlined process so far. Revised national and regional
guidelines for aggregate provision had been issued in June 2003 – an estimate of
the demand from the construction industry based on treasury models. This had
been broken down by region for aggregates, including marine sourced and recycled
or secondary aggregates. These figures had then been given to regional
assemblies and apportioned to counties. Figures had been calculated as per govt
guidance in relation to recent aggregate production trends, averaged 7 years
taking out highest and lowest levels of production. Surrey had been allocated
2.62m tonnes. SCC made representations that Surrey was constrained
environmentally and our allocation had been reduced to 2.5m tonnes. This
shortfall had not been reallocated to another county and was subsequently
reinstated. (Bucks and Oxon also had reductions). SCC pushed longer-term
sustainability issues – ie lack of sand in 20 yrs time.
South East England Aggregate Working Party (group of county councils) had
commissioned a study taking environmental capacity into account. Hope for a
significant production reduction following this report. Unfortunately, this may
take a year or two and would not, therefore, be ready in time for March.
Landfill and Restoration
PT asked how much of this process was driven by landfill requirement. HH
commented that it was not landfill sites SCC was looking for, but space for
treatment plants (which are inappropriate in green belt). SE (who is involved in
restoration) noted that 10-15 yrs ago landfill was important (‘void space’). Now
landfill is last resort in terms of waste. DL: despite increase of hardcore
recycling on building sites, there was still 50% left for inert fill. Landfill
was subject to tax and so much ‘inert’ is being diverted to alternative sites.
SE, replying to DB’s question, said that if 55 couldn’t be restored the
inability to restore would be a suitable reason for the Zone to be rejected.
CAMEL ‘should adopt the stance that we are living in a no fill world’. Licencing
agencies were getting stricter re content of material used for filling. However,
HH added that restoration means putting it back to an ‘acceptable afteruse’.
PT: Tree planting and bunds would have significant visual impact and would
not constitute restoration. DE suggested that restoration meant alteration in
real terms. Since extraction at Tapwood the water table had dropped and, indeed,
the River Mole no longer flooded at Betchworth bridge. This may seem
improvement, but the ecology of the whole area had altered. We were not against
change, but don’t want definitive alteration. Quarries were considered temporary
in guidelines, but the restoration to water rendered them a permanent alteration
to the landscape. SCC didn’t dispute that lakes don’t constitute temporary
fixture.
DL asked, for PMZs 60 and 55, if mineral extraction did have to go ahead,
what would CAMEL’s chosen restoration be, landfill or water. CAMEL’s response
was to have both sites returned to their current states.
HH agreed that Local Authorities had a duty to minimise impact and that small
stand-offs did not protect the residents.
Technical reports to be commissioned
- CBA (being extended to more sites)
- In-house noise engineers
- Environment Agency report (under consultation arrangement)
- Geology
- In-house traffic study.
DL: SCC not intending to commission any detailed reports, that would be for
the operator to do. Hydrology was an issue at Shagbrook and the
Environment Agency would pursue this. HH had asked Environment Agency to supply
information on hydrology across the county (EA had requested further hydrology
study on 23 out of the 26 sites), however, they refused as short on
funding/manpower. EA had raised particular concerns about Shagbrook which SCC
will pursue, notably contanimation of aquifer and drying out of Heath. NH asked
whether the SCC would commission another body to do the work; no they would not.
Furthermore, SCC would not preclude sites in absence of research. SE EA assesses
applications and gives response. Question as to whether landowner or contractor
should pay for this rather than public purse. Some operators were carrying out
this research now, SE stated, but that this was not currently the case with
PMZ60.
PT asked for bore hole information on PMZ55. Mineral reserves had been
established, but SE doesn’t know by whom. PT demonstrated how a geological
survey matched Frank’s assessment of sand on their plan. Concern that Franks are
willing to show their sand plan but not the bore hole reports. Were the bore
holes mentioned in the PMZ report from Frank’s information and if so, could PT
have a copy? SCC to revert to operators asking for further detail on geology.
SCC would make it available to public, however, they had not yet received a
formal submission from Franks. How much Franks disclosed was up to them. SCC
would respond shortly on whether they could verify our bore hole information
with their own.
DB noted that as PMZ 55 was so small, when taking margins into effect, the
removal of the zone wouldn’t impact on SCCs total sand reserve, so why not leave
it out.
SCC was waiting for a formal reply from Dungate Estates on their level of
interest. Adrian Saunders had told SE that he personally was not interested, but
his view was flexible. It was likely that they would want to pursue this
opportunity. Hanson had made varying representations, but Dungate Estates may
prefer another operator. Silica sand at PMZ60 was not good quality (although
this can be improved in processing), so the soft sand reserve was what was of
interest, but it was likely that any operator would want both. SE had stated to
Dungate Estates and Hanson that they should undertake their own hydrological
studies to be made available to SCC. SCC had no influence over the choice of
researchers but there was an assumed level of trust - any report would be
scrutinised. Dungate Estates had commented to SE that they were not interested
in landfill.
HH stated that she will refer back to noise engineers with points that
had been raised regarding both sites.
BS asked what consultation had taken place with the water company in light of
previous contanimation which had resulted in sleeving of bore hole. BS
considered that this was another matter relating to public trust. No meaningful
response ensued.
FR wondered how the Plan could be properly founded if there was no proper
research, for example, on the effect of hydrology on Reigate Heath? DL responded
that the PMZ report was a preliminary SEA report and that it was not the purpose
of SEA to answer every question.
SCC would accept any comment from CAMEL after 28th February.
Consolidated document from CAMEL of all points of objection for both sites
would be welcomed by SCC.
SCS